San Onofre outage costs hit $300 million, says operator

Share

Costs associated with the long-term shuttering of the San Onofre Nuclear Generating Station in North County top out at a more than $300 million, according to the plant’s operator.

Inspection and repair costs since the plant’s two reactors were shut down in January total $96 million as of Sept. 30, while the costs of replacing the plant’s power have risen to $221 million, according to Southern California Edison.

Edison is the operator and majority owner of the plant, which sits just north of Camp Pendleton near the San Diego-Orange County line. San Diego Gas & Electric owns a 20 percent share and receives one-fifth of its power.

The plant’s two active reactors were taken offline in January. One was shut down Jan. 9 for planned repairs while the other was shuttered abruptly Jan. 31 after a small leak of radioactive steam was detected. No one was injured by the leak but subsequent tests found fault with equipment in both reactors.

The U.S. Nuclear Regulatory Commission is reviewing a proposal from Edison to restart one of the reactors at 70 percent power for a trial period of five months, at which time more inspections would take place to ensure its safety. There are no immediate plans to restart the second reactor.

On Oct. 25, the California Public Utilities Commission voted to initiate a formal investigation into the long-term outages at the plant. It was unclear how long the investigation might take. As part of the investigation, the commission was expected to consider whether to order a refund to utility customers dating back to Jan. 1.

The $300 million-plus estimate on the costs associated with the plant’s shuttering came out of a third-quarter earnings statement released Thursday by parent company Edison International.