Steel pole project

Sentinel photo/Karen Brainard
Sentinel photo/Karen Brainard

Crews from Henkels and McCoy Construction work on Creelman Lane replace wood utility poles with steel, which are more durable, as part of San Diego Gas & Electric’s Transmission Reliability Project, said General Foreman Frank Roper. The project began on Monday, Aug. 20, and it will take crews about four weeks to replace the 11 wood poles on Creelman, he said. The distribution and transmission line leads to the Creelman substation.